ERCOT is tracking about 474 GW of large loads that want to connect, around 90% of them data centers1. The generator queue is about 463 GW1. Whoever supplies that load is mostly decided when the site is chosen.
We asked one question of every Texas large-load site in the GridLeads book: where does its power come from? 73 of 378 have generation of their own or beside them, 115 use the grid only, and 188 have no public answer.
By Maurice Tessier, GridLeads · · 426 large-load sites, 378 in Texas
39%of the 188 sites we could settle have generation (95% interval 32 to 46)
Why a power seller should care
1
The queue is enormous and mostly paper. ERCOT reported about 474 GW of large-load requests in June 20261, up from about 410 GW in March, which was itself 178 GW above the end of 20253. Data centers are 420.8 GW of it, or 90.2%2. ERCOT's own preliminary forecast shows about 367,790 MW of demand by 2032 against an all-time peak of 85,508 MW, and says it is not a prediction of what will be built4.
2
Pairing a load with a plant is now a regulated step. Senate Bill 6 (2025) directs the PUCT to set a large-load threshold of 75 MW or lower, requires a flat study fee of at least $100,000, and adds a review before a new large load can be net-metered with a plant that was already registered as stand-alone on 1 September 20255. By May 2026 the PUCT had approved two such arrangements, a 265 MW data center with a 265.5 MW wind farm in Armstrong County and a 760 MW data center with a 1,099 MW gas plant in Freestone County. Both require the plant to return its full output to the grid within 30 minutes of an ERCOT instruction6. In September 2026 the final interconnection rule dropped a proposed non-refundable fee of $50,000 per MW and replaced tiered study fees with a flat $100,000 fee7.
3
Building your own power is slow for big machines and quick for small ones. GE Vernova reports a gas equipment backlog and slot reservations of 116 GW9, and its chief executive put lead times on new heavy-duty gas turbine orders at about three years, while cautioning that the turbine is often not the binding constraint on a project10. Enverus estimates reciprocating engines, small and medium turbines and fuel cells reach operation in roughly 18 to 24 months, against up to 80 months for a large combined-cycle plant, and forecasts 5.0 GW of behind-the-meter demand in ERCOT from 2026 to 203011. Cleanview counts about 90 GW of generation announced for 59 behind-the-meter data centers in the US, of which about 2 GW is operating12.
What we checked, and how
Population: all 426 demand-side rows in the GridLeads project book, 378 in Texas and 48 in other states. The 106 supply-side rows are power plants and were left out.
Each site got one label: on-site (its own plant on the property), adjacent plant (a separate plant next door built or contracted to serve it), mixed (grid plus on-site or adjacent generation), grid only, or unknown. Battery-only sites are shown but left out of the percentages, because a battery moves power in time and does not make it. Back-up or emergency generators never count as on-site power.
A free keyword scan sorted every site into evidence groups. Research agents then read the sources for each site and had to give two word-for-word quotes per source, one naming the site and one stating the power arrangement. A separate checker re-fetched each page and ran our quote-grounding code on every answer that was not unknown: 105 were accepted, 39 downgraded (almost all to unknown) and none rejected.
What we found
One in five Texas large loads has generation, and half have no public answer.
Among the 188 sites we could settle, 39% have generation (95% interval 32 to 46). The unknowns are not random: two thirds of sites under 50 MW are unknown, against about one in four at 500 MW and over. Small plain data centers rarely say how they are fed, so the 39% is a better guide to large projects than to small ones.
On-site
Adjacent plant
Mixed
Grid only
Battery only
Unknown
Texas378 sites
44
115
188
Other states48 sites
6
21
17
All 378 Texas sites
On-site 44, 12%
Adjacent plant 15, 4%
Mixed 14, 4%
Grid only 115, 30%
Battery only 2, 1%
Unknown 188, 50%
The 190 sites with an answer (2 battery only)
On-site 44, 23%
Adjacent plant 15, 8%
Mixed 14, 7%
Grid only 115, 61%
Battery only 2, 1%
By kind of load
Industrial plants nearly always bring their own power (26 of 29), which fits steel mills and petrochemical works that already run on-site utilities. AI and hyperscale campuses come next at 22 of 48. Crypto mines (12 of 39) and plain data centers (21 of 96) mostly buy from the grid.
Share of settled sites with generation, by kind of load, all 426 sites. Dots are the share, bars the exact 95% interval.
By size
The share with generation climbs from 10% under 50 MW to 48% at 1,000 MW and over, and the unknown share falls as sites get bigger. Across data centers and AI campuses in every state, sites of 200 MW and above were 2.4 times as likely to have generation as smaller ones (36% against 15%; odds ratio 3.1, Fisher exact test p = 0.014). The loads that matter most to a generator are the ones most likely to arrive with supply attached.
Texas sites by stated size and power label, with the share of settled sites that have generation
Stated size
On-site
Adjacent plant
Mixed
Grid only
Unknown
With generation, of settled
Under 50 MW94 sites
2
1
0
27
64
10% 3 of 30
50 to 199 MW58 sites
2
2
1
19
34
21% 5 of 24
200 to 499 MW56 sites
3
6
3
25
19
32% 12 of 37
500 to 999 MW37 sites
4
3
1
21
8
28% 8 of 29
1,000 MW and over31 sites
3
3
5
12
8
48% 11 of 23
276 Texas sites that state a size. Cells are site counts and shading is each cell's share of its row. Two battery-only sites are not shown. Stated size is a soft number.
By stage
Sites still in development (39%) look much like live ones (45%), and the difference is not significant (p = 0.52). Self-supply is not only a legacy pattern: new projects choose it at a similar rate.
Share of settled Texas sites with generation, by stage. Announced, permitted and under-construction sites are pooled as in development.
Where
Generation-paired load clusters in a few counties: Brazoria, Calhoun, Harris, Pecos, Hood and Reeves. The four Dallas-Fort Worth core counties have 89 sites and none with generation. Two thirds of those are still unknown, so the 0 of 30 settled sites there (against 73 of 158 elsewhere in Texas, p below 0.001) shows where the unknowns need work, not that metro campuses cannot self-supply.
Texas counties with the most generation-paired sites
County
Sites
With generation
Grid only
Unknown
Brazoria
7
5
2
0
Calhoun
6
5
0
1
Pecos
6
4
2
0
Hood
6
4
2
0
Harris
32
4
9
19
Reeves
6
3
1
2
Bexar
24
3
3
18
Dallas, Collin, Tarrant and Denton
89
0
30
59
What this means for power generation companies
The Texas sites fall into three groups. Large and early means 200 MW or more and announced, permitted or under construction.
Already paired
73
median stated size 400 MW, 39 of the 73 state one
These sites have a supplier, and in the on-site cases they are one. For the owner of an adjacent plant they are a relationship to protect. For others they show how much of the large-load market closes before a sales conversation begins. The 14 mixed sites also still buy grid power, so they are customers for firming, backup capacity and expansion.
Grid only, large and early
42
median stated size 500 MW
Projects of real size whose sources show a grid connection and nothing else. They are the clearest targets for a power purchase agreement, a co-location offer on an existing plant, or bridging supply. A co-location with a plant already registered as stand-alone needs PUCT approval, and the two approvals so far carry a 30-minute recall condition on the plant6, so price that condition before pitching. Sites that need power sooner than about three years out may lean on smaller machines1011.
Unknown, large and early
25
of 188 unknown sites, median stated size 400 MW
Our sources are silent on how these sites will be fed. Silence is a sales opening as much as a research gap, and a first call is also the check, because silence in public sources does not prove a site has no supplier.
Competitors build in the plant counties. If your fleet sits in Brazoria, Calhoun, Pecos or Hood, much of the nearby large load already has its own supply and growth there looks like expansion of existing pairings. Elsewhere, the grid-only population is the opportunity.
Size is a screen. Below 200 MW, sites rarely bring generation and rarely say what they use. Above 1,000 MW about half do. Use size to separate who will build their own from who will buy.
This is a baseline for a disclosure wave. SB 6 requires large loads to disclose whether they are pursuing a substantially similar request elsewhere in Texas5, and the March 2026 PUCT proposal would have required disclosure of on-site backup generation able to serve at least half of demand8. We did not confirm that the backup requirement survived into the final rule.
Limits
Half of Texas is unknown. Many unknowns got a shallow read. The 39% assumes unknown sites resemble settled ones, which the size pattern suggests they do not.
Nothing here is verified grade. Our top grade needs an agency-authored official source plus an independent second author. No site meets it. Labels rest on company and press sources and passed a word-for-word quote check.
The book is not the queue. Our 378 sites are those in the GridLeads book, not the 474 GW ERCOT is tracking. The percentages describe the book and should not be scaled up to the queue.
Stated size is a soft number. Sizes often come from announcements, a campus can be listed as several rows, and no size was estimated when a source gave none. We report counts and medians, not totals.
Grid only does not mean no need. It means the sources show grid supply. The owner may still accept a bilateral deal or a backup plant.
Some rows may be out of date. A few sites carry a closure, an end of use or a bankruptcy on record and are flagged for cleaning. Labels are as of October 2026.
The statistics are exploratory. We ran many comparisons with no multiple-comparison correction, and small cells such as 5 of 37 have wide intervals.
Common questions
How many Texas large loads have their own power generation?
Of 378 Texas data centers, crypto mines and industrial plants in the GridLeads book, 73 (19%) have generation of their own or beside them (behind-the-meter or co-located): 44 on-site, 15 with an adjacent plant and 14 mixed. 115 (30%) use the grid only, 2 have only a battery, and 188 (50%) could not be settled from public sources. Among the 188 settled sites, 39% have generation (95% interval 32 to 46%).
Which kinds of site are most likely to bring their own power?
Industrial plants (26 of 29 settled sites), then AI and hyperscale campuses (22 of 48), crypto mines (12 of 39) and plain data centers (21 of 96). Bigger sites are more likely to: 10% of settled Texas sites under 50 MW have generation, against 48% at 1,000 MW and over.
How do you know whether a Texas data center has its own power?
Research agents read public sources for each site and gave two word-for-word quotes per source. A separate checker re-fetched each page and ran a quote-grounding check on every answer that was not unknown. 105 were accepted and 39 downgraded, almost all to unknown. Labels are research grade, not audited, and no site reaches our verified grade.
Does this cover ERCOT's full 474 GW large-load queue?
No. It covers the 378 Texas sites in the GridLeads book. ERCOT reported about 474 GW of large-load requests in June 2026. The percentages describe the book and should not be scaled up to that queue.
Where can I get the site-level details and contacts?
GridLeads has the details on all the large loads in this study and who to contact for each. Try the live demo at demo.gridleads.co or start at gridleads.co.
Get every large load, and who to contact
GridLeads has the details on all the large loads in this study and who to contact for each. Start with the live demo or book a call.
ERCOT, Trending Topics: Grid Reliability, Data Centers, and Net-Metering Arrangements, 1 June 2026. ercot.com
Utility Dive, Texas PUC adopts softened rules on data center interconnection, 21 September 2026. utilitydive.com
Foley & Lardner, Public Utility Commission of Texas Issues Proposed Rules for Large Load Interconnection, 31 March 2026. foley.com
GE Vernova, second quarter 2026 results, Form 8-K Exhibit 99. sec.gov
Power Engineering, Data centers drive record surge in GE Vernova power equipment orders as turbine slots tighten through 2030, 23 April 2026. power-eng.com
Enverus Intelligence Research, Behind-the-meter generation forecast: Skipping the queue, 11 August 2026 (an analyst forecast). enverus.com
Cleanview, Bypassing the Grid: How Data Center Developers Are Building Their Own Power Plants, 31 March 2026 (an analytics firm, secondary source). cleanview.co